Mud Creek Flood Reduction and Rehabilitation

Share Mud Creek Flood Reduction and Rehabilitation on Facebook Share Mud Creek Flood Reduction and Rehabilitation on Twitter Share Mud Creek Flood Reduction and Rehabilitation on Linkedin Email Mud Creek Flood Reduction and Rehabilitation link

Phase 1 of the Mud Creek project is complete. Please visit getinvolved.london.ca/mud-creek-phase-2 to learn more about Phase 2 and current work. 

An overhead photo of Mud Creek at Wonderland Road.


About this project

The City of London is reconstructing Mud Creek from the CN railway embankment south to Wonderland Road. The upcoming phase of construction includes an extensive restoration, tree plantings, habitat features and rehabilitation to an existing wetland feature.

The map below shows the extent of the phase 1b project work. Work is planned at the CN railway embankment and for portions of the Mud Creek corridor. The phase 1b reconstruction of Mud Creek is from the CN railway embankment southerly to Wonderland Road. It is noted that construction access roads will be required for construction.




About this project

The City of London is reconstructing Mud Creek from the CN railway embankment south to Wonderland Road. The upcoming phase of construction includes an extensive restoration, tree plantings, habitat features and rehabilitation to an existing wetland feature.

The map below shows the extent of the phase 1b project work. Work is planned at the CN railway embankment and for portions of the Mud Creek corridor. The phase 1b reconstruction of Mud Creek is from the CN railway embankment southerly to Wonderland Road. It is noted that construction access roads will be required for construction.



Phase 1 of the Mud Creek project is complete. Please visit getinvolved.london.ca/mud-creek-phase-2 to learn more about Phase 2 and current work. 

  • Construction Update - Spring, 2021

    Share Construction Update - Spring, 2021 on Facebook Share Construction Update - Spring, 2021 on Twitter Share Construction Update - Spring, 2021 on Linkedin Email Construction Update - Spring, 2021 link

    Phase 1a twin tunnel construction was successfully completed in the Spring of this year.

    The Phase 1b construction contract was posted for tender on the City’s Bids & Tenders website on May 25th, 2021, with the tender closing on June 9th, 2021.

    This upcoming phase of construction includes the new section of the creek downstream of the CN rail to Wonderland Road. Pre-construction work is anticipated to start in early July, until crews are able to officially begin in-water work after July 15th. Phase 1b includes an extensive restoration, tree plantings, habitat features and rehabilitation to an existing wetland feature. Construction is expected to be completed by the end of November.

  • Construction Update - Fall, 2020

    Share Construction Update - Fall, 2020 on Facebook Share Construction Update - Fall, 2020 on Twitter Share Construction Update - Fall, 2020 on Linkedin Email Construction Update - Fall, 2020 link

    Phase 1a of the Mud Creek Tunnel construction project is well underway. There has been a lot of activity within your neighbourhood and the City is sending you this update letter to help explain some of those activities and to inform you of what can be expected over the coming months. This type of construction project is unique and involves a considerable amount of preparation for heavy machinery and construction materials to be delivered to the site. The following activities are underway or have been completed to date:

    • Clearing of cut trees from the CN rail to Wonderland Road
    • Construction of Access Roads and Staging areas on the north and south side of the tracks
    • Temporary re-routing of the existing Mud Creek and smaller tributaries
    • Construction of temporary sending chamber/pits (large circular concrete


    Upcoming Construction Work:

    In each staging area, large circular concrete sending pits are being constructed on the north and south side of the railway embankment. These sending pits are temporary and are being constructed to facilitate a large boring machine that will tunnel the two large culverts (one by one) under the CN Rail tracks. Once the tunnel receiving chamber/pit is constructed on the south side, the contractor will move to the north side of the CN rail line (over the next 3 weeks). Then the tunnel boring machine will be delivered to the site by crane and the start of the tunnelling process will take place in November or December. This schedule is contingent upon CN Rail providing a full time staff member, otherwise known as a flagging person, to provide safe oversight of the CN rail lines during the tunnelling operations.

    During the tunnelling operation, there will be frequent delivery of large pipes and materials to the site on a daily basis for approximately 4 weeks. The current proposed tunneling operation will occur during the regular construction hours between 7:00 am and 7:00 pm but this may change to an additional night shift if the progression of the tunnel causes changes in the current schedule for a period of up to 2 weeks.

    The Phase 1a tunneling project is scheduled to be completed by spring 2021. Once the tunnel project is completed, the temporary sending pits will be removed and a concrete headwall will be constructed to allow the creek to flow through the tunnel. Please note that the creek will not be routed through the new tunnels until the channel is reconstructed as part of the next phase of the project.

    To keep you informed, the City will host a physically distanced public meeting in spring 2021 prior to commencing the Phase 1b natural channel rehabilitation project. This meeting will be held outdoors as a question and answer session with a maximum of 10 people per meeting. Multiple meetings may be scheduled depending on interest.

  • Construction Work Details

    Share Construction Work Details on Facebook Share Construction Work Details on Twitter Share Construction Work Details on Linkedin Email Construction Work Details link

    Pre-Construction Site Preparation Work

    As part of the phase 1a project work, the site required preparation work ahead of construction. This preparation work consisted of tree removals, tree trimming and stockpiling of tree material for use within the rehabilitated Mud Creek channel corridor as habitat enhancement features which will be part of the Phase 1b works. An example of a habitat enhancement feature would be the use of a partially buried tree log to create a riffle in the rehabilitated Mud Creek.

    Construction is anticipated to commence in September of 2020, and would include:

      • Tunnel two new culverts under the CN railway embankment at a lower elevation relative to the existing culvert;
      • Rehabilitate and retain the existing culvert under the CN railway embankment;
      • Tree removals/clearing from the CN Rail to Wonderland Road;


  • Renew London Interactive Map

    Share Renew London Interactive Map on Facebook Share Renew London Interactive Map on Twitter Share Renew London Interactive Map on Linkedin Email Renew London Interactive Map link

    Use the interactive map on Renew London to search your street name to find current information about your construction project and other city-wide road work.

  • Waze Navigation App

    Share Waze Navigation App on Facebook Share Waze Navigation App on Twitter Share Waze Navigation App on Linkedin Email Waze Navigation App link

    Download Waze, a free traffic and navigation app with local road closure information and real-time traffic alerts to get navigation assistance on the go.

    Thank you in advance for your cooperation. We look forward to completing these important infrastructure upgrades and channel rehabilitation in your area as we work towards building a more sustainable city.