Public update meeting
Please join the City of London for a virtual webinar to view construction plans, discuss impacts to your property, and to learn more about the project. Following the webinar, the presentation will be made available for download on the project website listed below.
Date: Tuesday, February 24, 2026
Time: Noon to 1:00 p.m.
Location: Register for the virtual webinar.
If you require any special accommodation in accessing the project information or online material, please contact the City project manager listed below, and we will work together to best share the information with you. If you have specific questions about potential impacts to your property, please contact the City project manager listed here.
About the project
The City of London is planning a construction project in your area to upgrade the Hyde Park Pumping Station. These upgrades will enable the station to accommodate increased flows associated with future development as well as from wet weather events, which are increasing in frequency and intensity.

Above: The map shows the project limits. The pumping station is located at 1439 Staffordshire Rd.
Proposed Work Details
- Construction of a new second wet well
- Installation of 4 new submersible pumps
- Repurposing the existing pump station building as a valve chamber
- Installing a new prefabricated building to house electrical equipment
- Upsizing the existing generator, complete with a noise reduction enclosure
Transportation Impacts
No road closures are anticipated for this project. The pathway between Staffordshire Road and Hyde Park Road may need to be closed for short periods to accommodate construction activities. Residents may notice increased traffic from construction vehicles and elevated noise levels in the area. We apologize for any inconvenience this may cause and appreciate your patience during this work.