Hansuld Street and Dale Street Infrastructure Renewal Project

Share Hansuld Street and Dale Street Infrastructure Renewal Project on Facebook Share Hansuld Street and Dale Street Infrastructure Renewal Project on Twitter Share Hansuld Street and Dale Street Infrastructure Renewal Project on Linkedin Email Hansuld Street and Dale Street Infrastructure Renewal Project link

Graphic of construction worker walking down residential street

About this project

The City of London is planning a construction project in the area of Hansuld Street and Dale Street to replace aging infrastructure that has exceeded its expected lifecycle.

This project includes:

  • Watermain replacement
  • Water Service replacement to property line
  • Sanitary sewer replacement
  • Storm sewer replacement
  • Partial replacement of existing private drain connections
  • Tree removals
  • New asphalt road surface

Construction is expected to start in spring 2022 and is anticipated to last until fall 2022 with some minor clean-up work in spring/summer of 2023.

PROJECT DESIGN UPDATE

Please note the initial proposed design of the Hansuld Street and Dale Street infrastructure renewal project has been updated to remove the sidewalk as part of the project. The removal of the sidewalk from the design will result in fewer tree removals. Please refer to the following tree removal list:

Updated tree removal list

This table is an update to the one provided within Presentation 3 - Tree Impacts and Protection.

LocationSpeciesTrunk
diameter
Reason
1705 Hansuld StBasswood20- 120 mmTree health and construction - conflict with watermain line
1653 Hansuld StBlue Spruce120 mmConstruction - conflict with water service and poor location
1652 Hansuld StAutumn Blaze Maple290 mmTree health and construction - conflict with water service
1678 Hansuld StGreen Spruce430 mmConstruction - tree may need to be removed depending on grading and watermain installation. Need for tree removal to be confirmed during construction.

Surface reconstruction and tree assessment report maps are available upon request. Please contact the Project Manager.

Above: The above map shows the project limits. Work is planned on Hansuld Street, from Second Street to Dale Street, and on Dale Street, from Second Street to Hansuld Street.


Ongoing public engagement

The project team has recorded a narrated Project Update Meeting (PUM) for residents to learn about project details and impacts. The video presentation has been split into three parts and can be accessed on the right-hand side of the page under "Project Update Meeting - Narrated Presentation."

It's also possible to access the PowerPoint presentation used during the PUM on the right-hand side of the page under "Project Update Meeting - PowerPoint Slides."

You can leave any questions or comments below. Also, please don't hesitate to contact the project manager if you have any questions about the information in the Project Update Meeting:

Project Lead

Name: Dave Chromczak
Organization: City of London
Phone: 519-661-2489 x 8439
E-mail: dchromcz@london.ca


Graphic of construction worker walking down residential street

About this project

The City of London is planning a construction project in the area of Hansuld Street and Dale Street to replace aging infrastructure that has exceeded its expected lifecycle.

This project includes:

  • Watermain replacement
  • Water Service replacement to property line
  • Sanitary sewer replacement
  • Storm sewer replacement
  • Partial replacement of existing private drain connections
  • Tree removals
  • New asphalt road surface

Construction is expected to start in spring 2022 and is anticipated to last until fall 2022 with some minor clean-up work in spring/summer of 2023.

PROJECT DESIGN UPDATE

Please note the initial proposed design of the Hansuld Street and Dale Street infrastructure renewal project has been updated to remove the sidewalk as part of the project. The removal of the sidewalk from the design will result in fewer tree removals. Please refer to the following tree removal list:

Updated tree removal list

This table is an update to the one provided within Presentation 3 - Tree Impacts and Protection.

LocationSpeciesTrunk
diameter
Reason
1705 Hansuld StBasswood20- 120 mmTree health and construction - conflict with watermain line
1653 Hansuld StBlue Spruce120 mmConstruction - conflict with water service and poor location
1652 Hansuld StAutumn Blaze Maple290 mmTree health and construction - conflict with water service
1678 Hansuld StGreen Spruce430 mmConstruction - tree may need to be removed depending on grading and watermain installation. Need for tree removal to be confirmed during construction.

Surface reconstruction and tree assessment report maps are available upon request. Please contact the Project Manager.

Above: The above map shows the project limits. Work is planned on Hansuld Street, from Second Street to Dale Street, and on Dale Street, from Second Street to Hansuld Street.


Ongoing public engagement

The project team has recorded a narrated Project Update Meeting (PUM) for residents to learn about project details and impacts. The video presentation has been split into three parts and can be accessed on the right-hand side of the page under "Project Update Meeting - Narrated Presentation."

It's also possible to access the PowerPoint presentation used during the PUM on the right-hand side of the page under "Project Update Meeting - PowerPoint Slides."

You can leave any questions or comments below. Also, please don't hesitate to contact the project manager if you have any questions about the information in the Project Update Meeting:

Project Lead

Name: Dave Chromczak
Organization: City of London
Phone: 519-661-2489 x 8439
E-mail: dchromcz@london.ca


Submit your questions or comments here.