Foster Avenue and Upper Avenue Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link

About this project

The City will be reconstructing Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive to replace and improve the quality and reliability of water, sewer and road infrastructure.

This project includes:

  • Watermain replacement including water service renewal to the property line
  • Storm sewer replacement
  • Partial replacement of existing private drain connections
  • Sidewalk replacement
  • New concrete curbs and gutters
  • New asphalt road surface
  • New rain gardens (green infrastructure) in the boulevard.

Construction is expected to start in spring 2021 and is anticipated to last until fall 2021 with some minor clean-up work in 2022.

The City of London will reconstruct Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive. For more information, please contact Jeff Conrad at jconrad@london.ca or by calling 519-661-2489 x 0016


Above: The above map shows the project limits. The City of London will reconstruct Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive.


Upcoming public engagement

The project team will record a narrated Project Update Meeting (PUM) for residents to learn about project details and impacts in January. The video presentation will be split into several parts and accessible on the right-hand side of the page under "Project Update Meeting - Narrated Presentation" (this section will be created when the materials are posted.)

It will also be possible to access the PowerPoint presentation used during the PUM on the right-hand side of the page under "Project Update Meeting - PowerPoint Slides" (this section will be created when the materials are posted.)

You can leave any questions or comments below. Also, please don't hesitate to contact the project manager if you have any questions or feedback:

Jeff Conrad

Technologist II

jconrad@london.ca

519-661-2489 x 0016

About this project

The City will be reconstructing Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive to replace and improve the quality and reliability of water, sewer and road infrastructure.

This project includes:

  • Watermain replacement including water service renewal to the property line
  • Storm sewer replacement
  • Partial replacement of existing private drain connections
  • Sidewalk replacement
  • New concrete curbs and gutters
  • New asphalt road surface
  • New rain gardens (green infrastructure) in the boulevard.

Construction is expected to start in spring 2021 and is anticipated to last until fall 2021 with some minor clean-up work in 2022.

The City of London will reconstruct Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive. For more information, please contact Jeff Conrad at jconrad@london.ca or by calling 519-661-2489 x 0016


Above: The above map shows the project limits. The City of London will reconstruct Foster Avenue, from Edinburgh Street to Riverside Drive; and Upper Avenue, from Foster Avenue to Riverside Drive.


Upcoming public engagement

The project team will record a narrated Project Update Meeting (PUM) for residents to learn about project details and impacts in January. The video presentation will be split into several parts and accessible on the right-hand side of the page under "Project Update Meeting - Narrated Presentation" (this section will be created when the materials are posted.)

It will also be possible to access the PowerPoint presentation used during the PUM on the right-hand side of the page under "Project Update Meeting - PowerPoint Slides" (this section will be created when the materials are posted.)

You can leave any questions or comments below. Also, please don't hesitate to contact the project manager if you have any questions or feedback:

Jeff Conrad

Technologist II

jconrad@london.ca

519-661-2489 x 0016

Do you have a question for the Project team?

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Why don't you ask a question?