2024 Channel Reconstruction
The City’s 2024 channel project will include approximately 800 linear metres of natural channel reconstruction from the CN Rail embankment northerly to Oxford Street. This channel will be widened to approximately 60 meters wide and will be up to 2 meters deeper than the current elevation to reduce flooding on Oxford Street and surrounding properties. This work will support this year’s 2023 construction of a new culvert pipe underneath Oxford Street and connect to the newly reconstructed Phase 1 Mud Creek channel section between the CN Rail and Wonderland Road in 2021/2022.
Share 2024 Channel Reconstruction on Facebook
Share 2024 Channel Reconstruction on Twitter
Share 2024 Channel Reconstruction on Linkedin
Email 2024 Channel Reconstruction link