Share East London Link on FacebookShare East London Link on TwitterShare East London Link on LinkedinEmail East London Link link
Project updates
Phase 4 – Oxford Street: Crews are completing roadwork, sidewalks and landscaping on the south side of Oxford Street this year. Work on the north side, between Highbury Avenue and Second Street, is scheduled to begin in January 2026. Lane restrictions and detours will be in place through September 2026.
Phase 3C – Oxford to Highbury: Most construction will wrap up in 2025, with final paving and bus lane painting planned for spring/summer 2026.
Phase 3B – Highbury Bridge: Construction on the Highbury Bridge will continue through winter and into 2026.
Phase 5 (2026–2027): Phase 5 will complete the final stretch along Dundas Street, connecting Wellington Street in the south to Oxford Street in the east. This work will finish the remaining link of the east leg of the project.
Map of East London Link Construction Phasing
About this project
The East London Link is a multi-year project that will revitalize more than 6 km of road from Downtown to Fanshawe College. The project will add transportation and transit improvements above ground, while repairing and replacing aging sewers, watermains and other underground infrastructure. The East London Link has received funding commitments from the Government of Canada and the Province of Ontario to support 10 transit and transit-supportive projects.
Centre-median
For both curbside and centre-running configurations, rapid transit corridors require a centre-median to maintain safe, frequent, and reliable transit operations. As a result, left-turning movements will be restricted to signalized intersections. Driveways and unsignalized side streets will change to right-in/out access.
This change may require local businesses to alter their delivery and/or access routes to and from both Highbury Avenue and Oxford Street as part of the East London Link project.
King Street Traffic Update
LTC buses are now travelling in both directions (westbound and eastbound) on King Street between Old East Village and Downtown. Unless you're driving an LTC bus, you should ONLY be travelling in ONE direction on King Street - that's eastbound!
Phase 3A East of the East London Link is currently in the tendering stage, which means the City is asking construction companies to submit bids to do the work. Once a contractor is selected, construction is expected to start in spring 2026.
Work will be completed in stages so crews can keep the project moving while still maintaining access to nearby homes, businesses and properties.
The first stage is expected to begin on Dundas Street at McCormick Boulevard and then move west. During this time, drivers can expect lane reductions and some turning restrictions.
Construction is planned for 2026–2027, with final surface paving scheduled for 2028.
Project status - Phase 4 (Oxford Street)
The East London Link Phase 4 construction is underway and will continue through 2025 and 2026.
Phase 4 of construction will be completed in stages to allow the work to progress while maintaining access to businesses and properties within the project limits. The first stage of construction started on the south side of Oxford Street from the eastern limit of the project to Roehampton Avenue, requiring lane reductions and turning restrictions. The project will then progress to the subsequent stages with similar restrictions in place.
Pre-construction webinar
Thank you for joining the pre-construction webinar for the East London Link Phase 4. A copy of the presentation is now available and can be viewed by clicking here.
Previous Public engagement opportunities
The City of London hosted a virtual meeting on Wednesday, November 6 to present an overview of the project design, construction timeline, and other details, such as impact mitigation.
An in-person drop-in session was also hosted on Tuesday, November 12 at the City of London Major Projects Office.
A copy of the presentation is now available and can be viewed by clicking here.
Above: Map of East London Link Phase 4 (Oxford Street from Highbury Avenue to a few metres east of Second Street)
Above: Conceptual rendering of the East London Link Phase 4 on Oxford Street.
Project status - Phase 3B (Highbury Avenue Bridge)
Improvements to the Highbury Avenue Bridge will be completed as part of the East London Link Phase 3.
The project includes the reconstruction and widening of Highbury Avenue from Dundas Street to the north limit of the Highbury Bridge / CPKC overpass.
The road widening will transform Highbury Avenue North from a four-lane cross-section to a six-lane cross-section, with a dedicated centre-running rapid transit lane in each direction (northbound and southbound).
Above: A conceptual rendering of the Highbury Avenue Bridge as part of the East London Link Phase 3B.
A recording of the public update webinar hosted in October 2023 is available further down on this web page with additional information about the East London Link Phase 3 design.
Expected construction timeline:
Construction is underway and will continue through 2026, requiring reduced lanes on Highbury Avenue from just south of Dundas Street to the north limit of the Highbury Bridge / CPKC overpass.
The work will be completed in stages to continue to maintain road access while also allowing the project to progress as efficiently as possible.
Anticipated impacts:
This section of Highbury Avenue will remain open with reduced lanes and delays throughout the duration of the project.
Project status - Phase 3A West (Dundas Street)
Construction is nearing completion for Phase 3A West of the East London Link and Municipal Infrastructure Improvements project on Dundas Street between Egerton Street and McCormick Boulevard. Some carry-over and warranty work is expected to take place in 2026.
Above: Map of the approximate limits of the project.
Recording of the pre-construction webinar for Phase 3A West (Dundas Street)
Thank you for joining us virtually on Tuesday, March 19, for a pre-construction webinar for the East London Link Phase 3A West.
Project status - Phase 3C (Highbury Avenue)
The City of London began constructing Phase 3C of the East London Link and Municipal Infrastructure Improvements in February along Highbury Avenue North between Oxford Street and the north limit of the Highbury Avenue overpass, as well as on Oxford Street from a few metres east of the Highbury Avenue intersection to near Wistow Street. Finishing work to be completed by 2025, with surface paving to take place in 2026.
Above: A map of the project limits for East London Link Phase 3C
Recording of the pre-construction webinar for Phase 3C (Highbury Avenue)
Thank you for joining us virtually on Wednesday, February 21, for a pre-construction webinar for the East London Link Phase 3C.
Other work planned in 2024, include Phase 3A on Dundas Street between Egerton Street and McCormick Boulevard. Remaining phases of the East London Link project, including Phase 3B along the Highbury Bridge are tentatively planned for 2025 and 2026.
Anticipated impacts:
Drivers:
Reduced lanes through the project limits along Highbury Avenue and Oxford Street
Turning movement restrictions and delays
Access will be maintained to commercial and industrial areas as well as residences
Transit riders:
Some LTC stops may be impacted while this work is underway. Transit riders are advised to visit the LTC website for service updates during construction
People walking:
Sidewalk closures and restrictions may be required during construction
Safe pedestrian connections and wayfinding signs will be in place to guide people walking around the construction zones
Sidewalk access will be maintained on at least one side of the road throughout construction
Recording of the Public Information Centre for East London Link Phase 3
Work details
Construction in 2024 on phase 3 of the East London Link is expected to include:
Adding concrete platforms for future rapid transit stops on Dundas Street and Highbury Avenue
Widening Highbury Road bridge to implement dedicated rapid transit lanes
Adding a concrete median throughout the center of Dundas Street and Highbury Avenue
Underground water and sewer replacement
Intersection upgrades and full intersection replacements
Upgrades to landscaping where applicable
Various utility works
Design update
The Dundas Street portion of phase 3 of the East London Link was updated from centre-running bus lanes to curb-side bus lanes, to implement a design solution that benefits transit operation while reducing business and property impacts. As the project team refined the original designs, it was determined that curbside design can continue to provide higher order transit operations, while balancing the interests of businesses, drivers and local transit users along Dundas Street.
Above: A cross-section illustration of the new configuration for the Dundas Street portion of phase 3, between Egerton Street and Highbury Avenue
The main factors considered when switching to a curbside RT configuration were overall corridor operations and reducing business/property impacts:
Property impacts: The footprint of the project is reduced by adjusting to a curbside RT configuration. The center-running design was very impactful to businesses and properties. The number of properties affected by land acquisition needs has been reduced by approximately 40% as a result of this design change. Also, the size of land parcels that we still require are now considerably smaller. In some cases, the design was able to avoid building impacts that had been identified in the Environmental Assessment.
Local transit operations: With only one traffic lane, local buses must also use the bus-only lane. Center-running bus lanes mean local buses can ONLY stop at RT platforms. By moving the bus-only lanes to the curb, local buses now have the ability to offer additional local stop opportunities to better support riders with mobility issues.
RT stop spacing: Locating RT stop platforms in the median requires a much larger footprint at intersections than curbside RT stop platforms. Adjusting to a curbside configuration made it possible to fit an additional stop at Kellogg’s Lane. The EA concepts showed a stop spacing of 1.1 kms in this location, which does not support transit ridership and is cut in half with a curbside configuration.
Business access / operations: The curbside scenario provides improved access for businesses and also provides wider right turn movements for larger vehicles, such as delivery trucks. The design team continues to consult with businesses to understand their business access needs for both the ultimate design and during construction.
Near-final designs will be shared in detail this fall at an upcoming Public Information Centre meeting.
Rapid transit bus shelter
Installation of new rapid transit shelters is underway at various locations across the East London Link, Downtown Loop and Wellington Gateway corridors.
If you wish to receive email updates from the City of London about the East London Link project, sign-up by clicking here.
Project updates
Phase 4 – Oxford Street: Crews are completing roadwork, sidewalks and landscaping on the south side of Oxford Street this year. Work on the north side, between Highbury Avenue and Second Street, is scheduled to begin in January 2026. Lane restrictions and detours will be in place through September 2026.
Phase 3C – Oxford to Highbury: Most construction will wrap up in 2025, with final paving and bus lane painting planned for spring/summer 2026.
Phase 3B – Highbury Bridge: Construction on the Highbury Bridge will continue through winter and into 2026.
Phase 5 (2026–2027): Phase 5 will complete the final stretch along Dundas Street, connecting Wellington Street in the south to Oxford Street in the east. This work will finish the remaining link of the east leg of the project.
Map of East London Link Construction Phasing
About this project
The East London Link is a multi-year project that will revitalize more than 6 km of road from Downtown to Fanshawe College. The project will add transportation and transit improvements above ground, while repairing and replacing aging sewers, watermains and other underground infrastructure. The East London Link has received funding commitments from the Government of Canada and the Province of Ontario to support 10 transit and transit-supportive projects.
Centre-median
For both curbside and centre-running configurations, rapid transit corridors require a centre-median to maintain safe, frequent, and reliable transit operations. As a result, left-turning movements will be restricted to signalized intersections. Driveways and unsignalized side streets will change to right-in/out access.
This change may require local businesses to alter their delivery and/or access routes to and from both Highbury Avenue and Oxford Street as part of the East London Link project.
King Street Traffic Update
LTC buses are now travelling in both directions (westbound and eastbound) on King Street between Old East Village and Downtown. Unless you're driving an LTC bus, you should ONLY be travelling in ONE direction on King Street - that's eastbound!
Phase 3A East of the East London Link is currently in the tendering stage, which means the City is asking construction companies to submit bids to do the work. Once a contractor is selected, construction is expected to start in spring 2026.
Work will be completed in stages so crews can keep the project moving while still maintaining access to nearby homes, businesses and properties.
The first stage is expected to begin on Dundas Street at McCormick Boulevard and then move west. During this time, drivers can expect lane reductions and some turning restrictions.
Construction is planned for 2026–2027, with final surface paving scheduled for 2028.
Project status - Phase 4 (Oxford Street)
The East London Link Phase 4 construction is underway and will continue through 2025 and 2026.
Phase 4 of construction will be completed in stages to allow the work to progress while maintaining access to businesses and properties within the project limits. The first stage of construction started on the south side of Oxford Street from the eastern limit of the project to Roehampton Avenue, requiring lane reductions and turning restrictions. The project will then progress to the subsequent stages with similar restrictions in place.
Pre-construction webinar
Thank you for joining the pre-construction webinar for the East London Link Phase 4. A copy of the presentation is now available and can be viewed by clicking here.
Previous Public engagement opportunities
The City of London hosted a virtual meeting on Wednesday, November 6 to present an overview of the project design, construction timeline, and other details, such as impact mitigation.
An in-person drop-in session was also hosted on Tuesday, November 12 at the City of London Major Projects Office.
A copy of the presentation is now available and can be viewed by clicking here.
Above: Map of East London Link Phase 4 (Oxford Street from Highbury Avenue to a few metres east of Second Street)
Above: Conceptual rendering of the East London Link Phase 4 on Oxford Street.
Project status - Phase 3B (Highbury Avenue Bridge)
Improvements to the Highbury Avenue Bridge will be completed as part of the East London Link Phase 3.
The project includes the reconstruction and widening of Highbury Avenue from Dundas Street to the north limit of the Highbury Bridge / CPKC overpass.
The road widening will transform Highbury Avenue North from a four-lane cross-section to a six-lane cross-section, with a dedicated centre-running rapid transit lane in each direction (northbound and southbound).
Above: A conceptual rendering of the Highbury Avenue Bridge as part of the East London Link Phase 3B.
A recording of the public update webinar hosted in October 2023 is available further down on this web page with additional information about the East London Link Phase 3 design.
Expected construction timeline:
Construction is underway and will continue through 2026, requiring reduced lanes on Highbury Avenue from just south of Dundas Street to the north limit of the Highbury Bridge / CPKC overpass.
The work will be completed in stages to continue to maintain road access while also allowing the project to progress as efficiently as possible.
Anticipated impacts:
This section of Highbury Avenue will remain open with reduced lanes and delays throughout the duration of the project.
Project status - Phase 3A West (Dundas Street)
Construction is nearing completion for Phase 3A West of the East London Link and Municipal Infrastructure Improvements project on Dundas Street between Egerton Street and McCormick Boulevard. Some carry-over and warranty work is expected to take place in 2026.
Above: Map of the approximate limits of the project.
Recording of the pre-construction webinar for Phase 3A West (Dundas Street)
Thank you for joining us virtually on Tuesday, March 19, for a pre-construction webinar for the East London Link Phase 3A West.
Project status - Phase 3C (Highbury Avenue)
The City of London began constructing Phase 3C of the East London Link and Municipal Infrastructure Improvements in February along Highbury Avenue North between Oxford Street and the north limit of the Highbury Avenue overpass, as well as on Oxford Street from a few metres east of the Highbury Avenue intersection to near Wistow Street. Finishing work to be completed by 2025, with surface paving to take place in 2026.
Above: A map of the project limits for East London Link Phase 3C
Recording of the pre-construction webinar for Phase 3C (Highbury Avenue)
Thank you for joining us virtually on Wednesday, February 21, for a pre-construction webinar for the East London Link Phase 3C.
Other work planned in 2024, include Phase 3A on Dundas Street between Egerton Street and McCormick Boulevard. Remaining phases of the East London Link project, including Phase 3B along the Highbury Bridge are tentatively planned for 2025 and 2026.
Anticipated impacts:
Drivers:
Reduced lanes through the project limits along Highbury Avenue and Oxford Street
Turning movement restrictions and delays
Access will be maintained to commercial and industrial areas as well as residences
Transit riders:
Some LTC stops may be impacted while this work is underway. Transit riders are advised to visit the LTC website for service updates during construction
People walking:
Sidewalk closures and restrictions may be required during construction
Safe pedestrian connections and wayfinding signs will be in place to guide people walking around the construction zones
Sidewalk access will be maintained on at least one side of the road throughout construction
Recording of the Public Information Centre for East London Link Phase 3
Work details
Construction in 2024 on phase 3 of the East London Link is expected to include:
Adding concrete platforms for future rapid transit stops on Dundas Street and Highbury Avenue
Widening Highbury Road bridge to implement dedicated rapid transit lanes
Adding a concrete median throughout the center of Dundas Street and Highbury Avenue
Underground water and sewer replacement
Intersection upgrades and full intersection replacements
Upgrades to landscaping where applicable
Various utility works
Design update
The Dundas Street portion of phase 3 of the East London Link was updated from centre-running bus lanes to curb-side bus lanes, to implement a design solution that benefits transit operation while reducing business and property impacts. As the project team refined the original designs, it was determined that curbside design can continue to provide higher order transit operations, while balancing the interests of businesses, drivers and local transit users along Dundas Street.
Above: A cross-section illustration of the new configuration for the Dundas Street portion of phase 3, between Egerton Street and Highbury Avenue
The main factors considered when switching to a curbside RT configuration were overall corridor operations and reducing business/property impacts:
Property impacts: The footprint of the project is reduced by adjusting to a curbside RT configuration. The center-running design was very impactful to businesses and properties. The number of properties affected by land acquisition needs has been reduced by approximately 40% as a result of this design change. Also, the size of land parcels that we still require are now considerably smaller. In some cases, the design was able to avoid building impacts that had been identified in the Environmental Assessment.
Local transit operations: With only one traffic lane, local buses must also use the bus-only lane. Center-running bus lanes mean local buses can ONLY stop at RT platforms. By moving the bus-only lanes to the curb, local buses now have the ability to offer additional local stop opportunities to better support riders with mobility issues.
RT stop spacing: Locating RT stop platforms in the median requires a much larger footprint at intersections than curbside RT stop platforms. Adjusting to a curbside configuration made it possible to fit an additional stop at Kellogg’s Lane. The EA concepts showed a stop spacing of 1.1 kms in this location, which does not support transit ridership and is cut in half with a curbside configuration.
Business access / operations: The curbside scenario provides improved access for businesses and also provides wider right turn movements for larger vehicles, such as delivery trucks. The design team continues to consult with businesses to understand their business access needs for both the ultimate design and during construction.
Near-final designs will be shared in detail this fall at an upcoming Public Information Centre meeting.
Rapid transit bus shelter
Installation of new rapid transit shelters is underway at various locations across the East London Link, Downtown Loop and Wellington Gateway corridors.
Share Is the presentation from Nov 4th available in a recorded format? on FacebookShare Is the presentation from Nov 4th available in a recorded format? on TwitterShare Is the presentation from Nov 4th available in a recorded format? on LinkedinEmail Is the presentation from Nov 4th available in a recorded format? link
Is the presentation from Nov 4th available in a recorded format?
MJS
asked
about 4 years ago
We will be posting the recording as soon as it's available from our Zoom account. It can take up to 24 hours to be ready, so we don't have it just yet. We'll send an email out to our subscriber list to let you know when it is ready. In the meantime, we're posting a PDF of the presentation to the website. Thanks for your interest in the project!
Spring/Summer 2022 - Beginning of Phase 1 construction
East London Link has finished this stage
Beginning of construction of Phase 1 - King Street between Wellington Street up to Lyle Street.
Fall 2022 - Public Information Centre for East London Link Phase 2
East London Link has finished this stage
From September 23 to October 7, check out the near final designs for phase 2 of the East London Link, and submit any questions or comments you may have to the project team.
March 1, 2023 - Preconstruction meeting for East London Link Phase 2
East London Link has finished this stage
A public meeting will be held to share detailed information of construction.
A link to the Zoom webinar will be provided on this page.
Early March 2023 - Construction begins
East London Link has finished this stage
East London Link Phase 2 construction begins between King/Lyle and Dundas/Egerton (includes Ontario Street between King and Dundas).
Summer/Fall 2023 - Construction continues for East London Link Phase 2
East London Link has finished this stage
Work is expected to wrap up in late fall of 2023 with minor carryover works in 2024.
Fall 2023 - Public update meeting to share near-final designs for Phase 3
East London Link has finished this stage
The City of London will present the near-final designs for Phase 3 of the East London Link, which is currently planned for construction in 2024. Information will include a detailed explanation of the design roll plans, as well as early information on construction.
February 2024 - Pre-construction engagement for Phase 3C
East London Link has finished this stage
Construction is planned to begin in February 2024 along Highbury Avenue between Oxford Street and the north limit of the Highbury Avenue overpass.
February 2024 - Construction begins for Phase 3C (Highbury Avenue North)
East London Link has finished this stage
Work is expected to wrap up in December 2024 with some planned carry-over and finishing works in 2025.
March 2024 - Pre-construction engagement for Phase 3A West
East London Link has finished this stage
Construction is planned to begin in March 2024 along Dundas Street between Egerton Street and McCormick Boulevard.
March 2024 - Construction underway for Phase 3
East London Link has finished this stage
This includes work for both Phase 3A West (Dundas Street) and Phase 3C (Highbury Avenue), which are anticipated to be completed in December 2024, with some planned carry-over work in 2025.
Fall 2024 - Public update meeting to share near-final designs for Phase 4
East London Link has finished this stage
The City of London hosted public engagement opportunities for Phase 4 of the East London Link in November 2024.
January 2025 - Construction begins for Phase 3B
East London Link has finished this stage
Construction is planned to begin on Highbury Avenue between Dundas Street and the north limit of the Highbury Bridge, as well as the CPKC overpass (weather permitting).
Spring/Summer 2025 - Phase 4 construction begins
East London Link is currently at this stage
East London Link Phase 4 construction begins on Oxford Street between Highbury Avenue and a few metres east of Second Street.
The personal information collected on this form is collected under the authority of the Municipal Act, 2001, S.O. 2001, c. 25, and will be used by the City of London and project partners to contact you in relation to the East London Link.
Questions about this collection should be addressed to Manager, Public Engagement, Major Projects, City of London at 251 Dundas Street, London, ON N6A 4L9. Tel: 519-930-3578, email: eastlondonlink@london.ca.