Burlington Street and Paymaster Avenue Reconstruction
Share Burlington Street and Paymaster Avenue Reconstruction on FacebookShare Burlington Street and Paymaster Avenue Reconstruction on TwitterShare Burlington Street and Paymaster Avenue Reconstruction on LinkedinEmail Burlington Street and Paymaster Avenue Reconstruction link
The public engagement opportunity for this project has ended. If you have any questions around construction, please contact Dave Chromczak at dchromcz@london.ca or by phone at 519-661-2489 x 8439.
About this project
The City is reconstructing Burlington Street, from Scenic Drive to Burlington Crescent; and Paymaster Avenue in its entirety to replace and improve the quality and reliability of water, sewer and road infrastructure.
Proposed Work Details:
Watermain replacement including water service renewal to the property line
Storm and sanitary sewer replacement
Partial replacement of existing private drain connections
New sidewalk installation on Paymaster Avenue and replacement of existing sidewalk on Burlington Street
Concrete curb and gutter replacement
New asphalt road surface.
Construction started in April 2021 and is anticipated to last until fall 2021 with some minor clean-up work in 2022.
Above: The above map shows the project limits. The City of London will reconstruct Burlington Street from Scenic Drive to Burlington Crescent and Paymaster Avenue in its entirety.
About this project
The City is reconstructing Burlington Street, from Scenic Drive to Burlington Crescent; and Paymaster Avenue in its entirety to replace and improve the quality and reliability of water, sewer and road infrastructure.
Proposed Work Details:
Watermain replacement including water service renewal to the property line
Storm and sanitary sewer replacement
Partial replacement of existing private drain connections
New sidewalk installation on Paymaster Avenue and replacement of existing sidewalk on Burlington Street
Concrete curb and gutter replacement
New asphalt road surface.
Construction started in April 2021 and is anticipated to last until fall 2021 with some minor clean-up work in 2022.
Above: The above map shows the project limits. The City of London will reconstruct Burlington Street from Scenic Drive to Burlington Crescent and Paymaster Avenue in its entirety.